The project was executed in the northern territories of the Caspian Sea in the Republic of Kazakhstan.
The scope of work includes the replacement of onshore oil and gas trunk lines, the swamp section and shallow water sections. 

 

It also includes upgrading of the 5 onshore valve stations, with valve replacements.

PROJECT DETAILS

815

MOBILISED

PERSONNEL

We mobilised mostly direct personnel such as: welders, grinders, riggers, and pipe fitters. As well as indirect  personnel such as: welding inspectors, welding supervisors, piping supervisors, HSE inspectors, and QA/QC inspectors.

6

DIFFERENT

NATIONALITIES

The following nationalities were mobilized on the project: Kazakhs, Italians, Thais, Romanians, Indians, and Turkish.

2015

THE STARTING DATE

OF THE PROJECT

The project started in March 2015 and was completed according the forecast at the end of June 2016.

CONTRACTORS AND FINAL CLIENTS