EPC CLUSTER 4
TOPSIDE
This contract was for the Procurement, Fabrication, Load-Out and Transportation of Topside for EPC Cluster 4 within the Kashagan Experimental Project, with execution of works in "Temir At" yard.
Briefly the Scope of Work consists of the following Endorsement of Detail Engineering Package:
• Procurement of project materials, Shop Drawings, Method Statements;
• Fabrication/Construction works by KCOI;
• Electrical/Instrumentation/Telecom Installation works by consortium partner
• Load – Out Procedures and Load – Out Operation by skidding a 1500 tons module on barge to be transported offshore.
PROJECT DETAILS
188
MOBILISED
PERSONNEL
For the project we mobilised the following personnel: Welders, Steel Fitters, Pipe Fitters, Riggers, Foremen, Welding Supervisors, Welding Inspectors, HSE Inspectors, QC Inspectors and Coordinators.
5
DIFFERENT
NATIONALITIES
Personnel of the following nationalities: Kazakhs, Italians, Indians, Filipinos and Thais.
2017
THE STARTING DATE
OF THE PROJECT
The project has an estimated duration of 3 years, with a delivery date for 2019.