top of page


ESKENE WEST
KASHAGAN PROJECT
Maintenance of the Power Station, Switchyard and Overhead lines distribution. Provision of technical specialists and support activities, maintenance and procurement service (spare parts), major inspections, assistance to OEM. Shutdowns and turnarounds activities.
PROJECT DETAILS
800
PEAK OF PERSONNEL
Throughout then duration of this project, we reached a peak number of 800 mobilized personnel to assist with the overall execution.
22
DIFFERENT
NATIONALITIES
Our group initially mobilised and continued mobilising Kazakh personnel together with highly skilled professionals from abroad like Engineers, Coordinators, Supervisors, and Electricians, Instrumental Technicians.
2009
THE STARTING DATE
OF THE PROJECT
The contract was over a period of 5 years and it was an AKCO Major Contract.
bottom of page